Grier Meadows Progress – Jan. 27, 2025

Posted By:John Boone

February 4, 2025

WEEK OF JANUARY 27 WORK SUMMARY

Street trees and sod were installed in phase 2 and along Frank Grier Rd. The planting strip in front of BMP 3 was fine graded and sodded, and the common area landscaping is now complete in phase 1. Once the phase 1 storm pipe video is approved, we can schedule the punchout.

Abernethy fine graded lot 80 in phase fixed the damaged water valves beside lot 55 in phase 2. They also installed the remaining conduit crossing for Duke in phase 4. Duke is expected to complete their install in phase 4 the week of 2/3. AT&T is scheduled to complete phase 4 install the week of 2/10.

The Grier’s sewer service applications and executed sewer easement were sent to the City, and they are reviewing the easement. Once approved, we can submit payment, and the City will schedule the work.